Question

A group of N people worked on a project. They finished 35% of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of N is:

  • A. 150
  • B. 23
  • C. 36
  • D. 140

Step-by-Step Explanation

We apply the standard work-equivalence chain rule formula:

M₁ Γ— D₁ Γ— H₁/W₁ = Mβ‚‚ Γ— Dβ‚‚ Γ— Hβ‚‚/Wβ‚‚

  • Initial State Parameters:

M₁ = N people, D₁ = 10 days, H₁ = 7 hours/day, W₁ = 0.35 (35% of the project)

  • Subsequent State Parameters:

10 people left, so:

Mβ‚‚ = N βˆ’ 10 people

Dβ‚‚ = 14 days

Hβ‚‚ = 10 hours/day

Remaining work:

Wβ‚‚ = 1 βˆ’ 0.35 = 0.65 (65% of the project)

  • Set Up and Solve the Equation:

(N Γ— 10 Γ— 7)/0.35 = ((N βˆ’ 10) Γ— 14 Γ— 10)/0.65

70N/0.35 = 140(N βˆ’ 10)/0.65

200N = 140(N βˆ’ 10)/0.65

200N Γ— 0.65 = 140(N βˆ’ 10)

130N = 140N βˆ’ 1400

10N = 1400

⟹ N = 140

Correct Option: D

πŸ’‘ FundaMakers Tip:

Relying on the structural Chain Rule fraction bypasses the need to compute arbitrary intermediate absolute metrics like total man-hours. Setting up direct proportional balances helps you eliminate terms quickly across the equals sign.

Time and Work Shortcuts & Tricks

Time and Work Questions Involving Workers Joining/Leaving

  • Concept: Workers join or leave while the work is in progress.
  • Key Idea: Calculate the work completed before and after the change.
  • Common Question: Find the remaining work or total time taken.
  • Approach: Use efficiency Γ— time = work for each stage.
  • CAT Focus: Tests work rates, efficiency, and proportional reasoning.
  • Tip: Divide the problem into separate time periods whenever the number of workers changes.
Share on XShare on WhatsApp
error: Content is protected !!

ENQUIRE NOW

Fill In The Form To Get A Quick Call From Our Team.

Stay Connected On

BOOK YOUR DEMO NOW!

BOOK YOUR DEMO NOW!