Question

Gautam and Suhani, working together, can finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work on that day to exactly make up for it. Then, the number of days required by the faster worker to complete the job working alone is:

Step-by-Step Explanation

  • Analyze the Work Deficit Balance:

Gautam and Suhani's combined normal daily work output matches a 20-day completion rate.

One day, Gautam reduces his work output to 60%, creating a 40% drop in his daily contribution. Suhani increases her output to 150%, creating a 50% increase in her contribution. Since this adjustment exactly maintains their schedule, Suhani's increase perfectly matches Gautam's decrease:

40% of Gautam = 50% of Suhani

0.40G = 0.50S

âźą S/G = 4/5

  • Calculate the standalone completion time:

This ratio shows that Gautam is the faster worker. Let us define their daily efficiencies as:

G = 5x units/day

S = 4x units/day

Combined Daily Efficiency = 5x + 4x = 9x units/day

Total Work (W) = 20 days Ă— 9x units/day

= 180x units

Time taken by Gautam alone = 180x/5x

= 36 days

Correct Answer: 36

đź’ˇ FundaMakers Tip:

Use the Work Balance Shortcut! If one worker's drop is balanced out by another worker's increase, their efficiency ratio is simply the inverse of their percentage changes (40% : 50% âźą 5 : 4). This approach bypasses simultaneous fractional setups entirely.

Share on XShare on WhatsApp
error: Content is protected !!

ENQUIRE NOW

Fill In The Form To Get A Quick Call From Our Team.

Stay Connected On

BOOK YOUR DEMO NOW!

BOOK YOUR DEMO NOW!